Naval Hospital at Camp Pendleton

Delivered Six Months Ahead of Schedule & $100 Million Under Budget
The design-build team has been held to a high standard and has risen to, and in many cases, exceeded the requirements of the contract to the benefit of the Government. Our team would gladly work with Clark again in the future.
William Hepler, Contracting Officer, Naval Facilities Engineering Command

The 500,000-square-foot Naval Hospital at Camp Pendleton houses inpatient medical facilities with 54 patient rooms and up to 60 beds, ancillary departments, emergency care units, primary care units, specialty care clinics, and support spaces and facilities for non-ambulatory patients who require stays in excess of 24 hours. Clark, as part of a joint venture team, met the client's aggressive schedule, delivering the project over six months ahead of the Navy’s target schedule more than $100 million under budget.

The Naval Hospital at Camp Pendleton will serve some 70,000 active duty and veteran Marines, sailors and family members. In addition to the hospital facilities, the project included a central utility plant, site development for the 70-acre campus, and more than 2,500 parking spaces, including a 1,500 space, multi-level parking structure. A pedestrian bridge connects the parking structure to the second floor of the hospital.

The new hospital also represents a new standard for federal healthcare construction. In addition to the traditional responsibilities of a design-builder, NAVFAC sought a partner who also could handle the project’s full medical planning, including all equipment procurement, coordination, installation, and training. 

Working together with the architects and the Navy Medicine West user groups, the Clark/McCarthy joint venture team designed a full suite of equipment with a detailed room contents list, including Basis Of Design specifications for  more than 20,000 pieces of equipment. Once the design was finalized, the team worked with NAVFAC and equipment manufacturers to develop a funding and procurement schedule. After the client selected a specific piece of equipment, Clark/McCarthy secured a purchase order from the manufacturer, coordinated lead times with the construction schedule, and arranged for just-in-time delivery to the site.

From the MRI unit, to the blood analyzers, operating room integration, patient beds, and trash cans, the Clark/McCarthy team was responsible for every step: design, planning, equipment selection, procurement, installation, training, and warranties. Using this turnkey delivery – which is traditionally parceled out by the client to multiple subcontractors - the team maximized quality, minimized extra costs, and expedited the construction schedule.  

Meeting the aggressive schedule required that construction start prior to the completion of design documents. Phased packages supported construction and were vital to completing the design 13 months after the Notice to Proceed.

BIM

In addition to the phased design, BIM allowed the design team early access to congested areas. Clash detection prior to construction improved work flow, eliminated field conflicts, and enabled the team to perform quality control through all phases of the project. The design process also fostered constructability reviews between the construction team and the teamed subcontractors. Construction details were reviewed, challenged, and in some cases revised to allow easier and cleaner construction.

Safety

The team instituted a series of daily, weekly, and monthly initiatives to maintain a focus on safety. Each was designed to reflect an overall philosophy of positive reinforcement, putting people first, and diligent correction. The positive safety culture at Camp Pendleton permeated throughout the workforce and was shared equally by front-line craftsmen and top Navy officials.

There were zero lost-time incidents for the entire duration of the project, more than 2.6 million man-hours.

Sustainability

The project earned LEED Gold certification. This achievement was realized due to the incorporation of a myriad of sustainable features, including green roofs, solar cells, horizontal and vertical sun screens, maximized use of recycled materials, and low-flow plumbing fixtures. All of these features will reduce overall hospital energy consumption. The garage's top level features photovoltaic cells providing electricity for the hospital and garage as well as shade for the cars parked underneath. The Navy initially requested LEED Silver certification, but the project team was able to jump to LEED Gold for no additional cost.

Small Business

Seventy-five percent of all contracts were awarded to small business subcontractors, including more than 45 percent to Service-Disabled-Veteran-Owned Small Businesses (exceeding the Government’s goals by almost $150 million for SDVOSB).

Awards: 
AGC of San Diego - Merit Award, Building Construction Public Work
Alliant Build America Award - Building/New Construction
Alliant Build America Award - Marvin M. Black Excellence in Partnering
BD+C Platinum Building Team Award
CMAA San Diego Project of the Year - New Building Over $35 Million
DBIA National Award of Merit
DBIA Western Pacific Region - Project of the Year
DBIA Western Pacific Region - Distinction Level Award, Projects in Progress
ENR Best Regional Projects - Healthcare
NAVFAC Best of the Best Safety Award
NAVFAC Safety Star Awards, 2011 & 2012
SAME San Diego Award of Excellence
  • ClarkBuilds
    ClarkBuilds From coast to coast, Clark has had the honor to construct the nation's top airports and their infrastructure.… t.co/PN84coFIsd
    August 19
  • ClarkBuilds
    ClarkBuilds Our Confluence team in #Denver received certificate of occupancy & welcomed the first tenants moving into the ultra… t.co/sAQRTpqj6U
    August 18