Client
City of Atlanta Department of Watershed Management
Location
Atlanta, Georgia
Completion Date
2019
Delivery Method
Construction Manager at Risk
Atlanta Water Supply Program Phase 1A and 2 connects the Bellwood Quarry to the Hemphill Pump Station and the Clayton Site adjacent to the Chattahoochee River. It includes a 5,569 linear-foot, 10.5-foot-diameter tunnel through hard rock. Phase 2 extends the tunnel to 15,000 linear-foot to the Clayton Site where a 30-foot-diameter by 350-foot-deep shaft served as the exit location for the tunnel boring machine. The project increases the City of Atlanta’s water storage capacity approximately tenfold.
Awards
2020 ENR Southeast Best Project Award (Water/Wastewater)
2020 ENR Global Best Project Award (Merit, Water/Wastewater)