The new terminal – completed ahead of schedule and on budget – ushers in a new era of air travel for the region. While the $1.5-billion design-build project offers the traveling public a total transformation, its greatest impact may be felt by the community closest to home. The team prioritized community engagement from the outset, exceeded ambitious small business participation goals, and implemented a first-of-its-kind workforce training program to deliver a facility that is uniquely Kansas City.

This February, the first flight departed from the new single terminal at Kansas City International Airport (MCI), marking the culmination of a five-year project that ushers in a new era of air travel in the region. The largest single infrastructure project in Kansas City history, the 1.1 million-square-foot design-build project replaced the original three-terminal facility to streamline airport operations and improve the passenger experience. Design and construction efforts for the new terminal began in 2018, and the project broke ground in March 2019.

To usher in a new era of air travel for the region, the City of Kansas City needed a partner who could develop a project vision to meet the needs of the community and assemble the best team to deliver this critical infrastructure project. With capabilities that span the full asset lifecycle, Clark was the perfect partner for Kansas City.

Developed by Clark-affiliate Edgemoor Infrastructure and Real Estate and constructed by a joint venture team led by Clark Construction Group in partnership with The Weitz Company and Clarkson Construction Company (CWC), the new terminal was delivered ahead of schedule and on budget while providing a significant economic boon to the local community.

Collaborative design process captures local culture, delivers functionality

The new H-shaped structure features two levels with clear wayfinding and sightlines and an adjacent 6,200-space parking structure that provides a seamless transition from parking to gates. Designed by Skidmore, Owings & Merrill (SOM) with adaptability and expansion in mind, the terminal opened with 40 gates and the capability to add 10 more gates in the future.

The team and the Kansas City Aviation Department (KCAD) prioritized community engagement from the project’s outset, hosting dozens of community design workshops and open-house sessions to solicit their input on the new terminal’s design.

In conjunction with this outreach effort, the construction team collaborated with SOM, the airport, and airlines through six design iterations to achieve $38 million in cost reductions while preserving the project scope and design intent. Through constructability reviews, the team optimized the volume of the space and maximized the efficiency of MEP systems. The central utility plant (CUP), originally designed to be a standalone building a third of a mile from the terminal, was moved inside the terminal, further improving MEP performance and improving energy efficiency as well as ease of maintenance. The cost savings gained through these constructability enhancements helped to fund additional features, including an automated parking system and cellular antenna for the garage, while maintaining the overall project budget.

While constructability reviews helped maximize the structure’s functionality, unique design details make the terminal shine. The new facility showcases Kansas City’s authentic culture, featuring nearly 50 local and global dining and shopping experiences, with 80% of the brands from the Kansas City region. The space also features $5.6 million of newly commissioned art, showcased through 28 unique installations – 19 created by artists who live in or have ties to the Kansas City area.

Drilling into details mitigates impact on airport operations

The airport’s original Terminal A was razed to make way for the new terminal and garage. At the same time, Terminals B and C, located adjacent to the project site, remained fully operational throughout the project.

From crane locations to air traffic control tower sightlines and safety protocols, CWC worked with SOM, MCI, and the Federal Aviation Administration (FAA) to plan every detail around ongoing airport operations.

Image

by the numbers

The team re-routed traffic flow, constructed two new roundabouts to accommodate visitors during the multi-year construction effort, and relocated existing utilities without impacting travelers.

No detail was overlooked – when the new utility corridor conflicted with existing underground communication cables for the air traffic control tower, the project team developed drawings to aid KCAD and the FAA with efforts to schedule and execute the cable relocation.

A grand and complex front entrance

The 800-foot-long terminal entrance, where travelers access airline ticket counters, baggage service, and security checkpoints, posed one of the biggest construction challenges on the project. The wide front overhang, supported by 65-foot-tall Y-columns and 115-foot-long box beams, is located above an elevated roadway with its own concrete reinforcement columns. 

“It’s a significant architectural element and a lot of time was spent studying the structure and how to design it and how to build it,” says Mark Goodwin, vice president with Clark and operations leader on the project.

The solution was to erect the precast wall in front of the terminal entrance before precast road-support columns and the roof's steel Y columns. The precast panels were first set as a standalone wall, temporarily supported, and then the steel structure was erected over it. The Y-columns were assembled on site and lifted as one piece. Once the precast wall and Y-columns were erected, the box beams were welded into the three contact points. The process was repeated for each of the 25 columns and beams down the length of the structure.

Image

Kansas City International Airport (MCI) New Single Terminal
The overhang of the 800-foot-long entry is supported by more than two dozen 65-foot-tall Y-columns and 115-footlong box beams.
Early trade contractor involvement streamlines schedule

Early in the design-build process, critical decisions eased workforce and scheduling challenges throughout construction. Major trades joined the team during the design phase, many under design-build subcontracts, to provide constructability input and facilitate the procurement of long-lead items. “Bringing trade contractors on early allowed shop drawings to progress in parallel with the design, streamlining the efficiency of material fabrication,” Goodwin explains. “We were issuing foundation packages, steel packages, curtainwall packages in a progressive nature that required an extraordinary amount of coordination between the design assist trade contractors and our design team.”

Keeping the massive project on track was essential, with the completion date scheduled to accommodate visitors to Kansas City for the NFL draft in April 2023. A phased construction plan divided the building into 17 sections along the structure’s expansion joints to establish critical milestones and clearly define workflows.

The terminal’s two structural systems – steel and cast-in-place concrete – divided the massive scopes between two trades to accommodate workforce needs and carefully factored in lead times for steel. The team also strategically pursued prefabrication of multiple trades, including unitized curtainwall, precast panels, and bathroom components, to reduce workforce needs on site.

Delivering on the promise of community transformation

More than 245 Kansas City-area firms contributed to the project, which generated over 6,500 design- and construction-related jobs. From the outset, the project team committed to reaching transformative levels of participation from both minorities and women, spurring economic growth in the region. The team implemented a series of programs to remove barriers that typically impact disadvantaged businesses from securing contracts and developed a first-of-its-kind workforce training program to build capacity in the local construction market. The workforce training program created a pathway to careers in the construction trades for 200 men and women. Those individuals went on to work more than 200,000 hours on the new terminal, earning more than $6.5 million in wages and benefits.

Through an intentional procurement strategy, 133 minority- and women-owned Kansas City-based firms were awarded contracts on the project totaling more than $320 million. The team exceeded its project participation goals on every front, ultimately achieving 25.4% MBE and 18.7% WBE participation for construction services, and 20.5% MBE and 16.4% WBE participation for professional services.

“Despite the unforeseen challenges of a global pandemic and supply chain shortages, they delivered on their promises, both to the city and to our greater community. This is a truly transformational project, as was promised from the start,” said Pat Klein, director of the Kansas City Aviation Department.

Image

Kansas City International Airport (MCI) New Single Terminal
Clark's Strategic Partnership Program, which debuted in Kansas City in 2018, is one of several programs the team implemented to reach transformative levels of small business participation.
New era for Kansas City air travel

The last flights into the old terminals arrived on February 27, with flights departing from the new terminal the following day.

“The proportion of [billion-dollar-plus projects] that are completed in a way that meets the promised benefits, happens on time, and arrives at or under budget, is less than 1%. So you've done something special here that we're all going to need to learn from in this country.”

- Pete Buttigieg, United States Department of Transportation Secretary

The opening was commemorated by a ribbon-cutting led by Kansas City Mayor Quinton Lucas and featuring US Department of Transportation Secretary Pete Buttigieg, Missouri Congressman Emanuel Cleaver, Missouri Governor Mike Parson, Kansas Lieutenant Governor David Toland, Kansas City Director of Aviation Pat Klein, and Edgemoor Infrastructure & Real Estate Senior Managing Director Geoff Stricker.

“In many ways, this airport is a model for similar efforts nationwide. Not only did you deliver the largest infrastructure project this city has ever seen – you did it on time and budget while supporting over 5,000 construction jobs and working with over a hundred women- and minority-owned businesses,” said US Transportation Secretary Pete Buttigieg. “There’s a new body of research that’s come out analyzing billion-dollar plus projects. The proportion of them that are completed in a way that meets the promised benefits, happens on time, and arrives at or under budget, is less than 1%. So you’ve done something special here that we’re all going to need to learn from in this country.”