I-5 Pavement Rehabilitation

Santa Clarita, CA
California Department of Transportation – District 7
Contract Value: 
Year Completed: 

Atkinson will remove and replace 16 miles of pavement north of the I-5/SR-14 Interchange in Santa Clarita. The project team will replace 2,800 precast roadway panels, and will place approximately 175,000 cubic yards of concrete to construct the new lane pavement. Originally planned to be performed under nightly temporary (coned) lane closures, the Atkinson team instead developed a staging plan to maximize the amount of work that can be performed during the day and behind positive construction barriers to ensure the safest and most efficient work environment.